A When calculating months and hours of experience, a unique (non-overlapping) month is a month where only one project is counted. For example:
 
Project Dates Project
Length
Project
Hours
     Project 1: 01/03 to 06/03 6 1000
     Project 2: 03/03 to 07/03 5 500
Subtotal 11 1500
     Less Overlap (03/03 to 06/03) 4  
Total Months/Hrs Counted 7 1500

As you see from this example, the months where the projects overlap are counted once. Additionally, all of the hours worked on both projects are counted. The months of experience do not have to be consecutive.

Connect With Us

LinkedIn-Button     Facebook-Button     Twitter-Button

Chapter Membership

Total Members 762
New members this year 44
PMP® Members 511
CAPM® Members 12
PgMP® Members 2
PMI-SP® Members 1
PMI-RMP® Members 6
PMI-ACP® Members 14
PfMP® Members 1
PMI-PBA® Members 1
PMP/CAPM/PgMP/PMI-SP/PMI-RMP/PMI-ACP/PfMP/PMI-PBA are registered marks of the Project Management Institute, Inc.

Stay Informed!

Not a chapter member yet? Register for the newsletter here to stay informed of the exciting chapter news and events.
captcha